Precision machining subcontractor · 1 site, 42 CNC machines · 140 employeesThis War Map shows how we turn an operational review into an implementation plan. The dates show a possible sequence; the scope and schedule of a real engagement are agreed with you.
Implementation plan
What to fix first, how long it takes, and who signs what. 8 initiatives across 4 departments. €530-760K illustrative annual gross value.
Priorities at a glance
- 8 initiatives across 4 departments
- €530K to €760K in illustrative annual gross value
- Sample target: supplier price requests and NC tracker live in month 1
- Target: new-part quotes sent within 3 days, priced by the methods team from a prepared file
Automation Opportunity Map
The goal is not to add AI on top of chaos. The goal is to turn repeated fires into infrastructure: context assembled automatically, decisions routed to the right level, exceptions escalated only when human judgment is actually needed. The figures below show direct value by initiative. Broader operational value is modeled separately.
Matching and updates use deterministic rules. An agent can classify a free-text request, gather records or draft a response. Software-enforced access, validation, duplicate handling and named human approvals govern consequential actions.
The two estimates (direct value by initiative; projected annual value by operational effect) are alternative, overlapping views. Do not add them. Ranges are teaching assumptions without source measurements: volumes, time, loaded cost and error cost require validation. Investment, operation and adoption ramp remain to be deducted.
Implementation Timeline
Weeks are relative to implementation start; months represent four four-week blocks. Dependent work can be prepared in parallel with test fixtures, but production release waits for sync acceptance. This is a scenario schedule.
Supplier Price Requests
Weeks 2 to 4
NC and 8D Tracker
Weeks 2 to 5
Quote Preparation
Weeks 3 to 9
FAI Pack
Weeks 4 to 8
Capacity View
Weeks 4 to 11
Revision Check
Weeks 5 to 8
Delivery-date Promise
Weeks 10 to 13
OEM Portal Updates
Weeks 12 to 14
Quote-to-actual Margin Feedback
Weeks 14 to 16
Month 1: Supplier price requests and the NC tracker go live. Quote preparation starts on aerospace RFQs, with Patrick checking every prepared file.
Month 2: Quote preparation covers all new-part RFQs. FAI pack and revision check in production, with quality signing every report. Actual times start flowing into Silog during the shift.
Month 3: The capacity view replaces the morning Excel rebuild. Target: compare quote turnaround and RFQ response rate with the June baseline.
Month 4: Delivery-date promise and portal updates in use. A second planner runs a full week. Target: confirm released capacity and on-time delivery against the scorecards without double counting.
Projected Annual Value
Direct initiative value is the sum of the eight initiatives; the projected figure adds effects that cross them, such as more quotes answered on time. Extra won work is counted at margin, not revenue, and assumes machine capacity is available. Released hours go back to estimating and engineering, with no headcount reduction assumed.
How much time could this free up?
Choose one non-overlapping task category and the people who actually perform it. These inputs are scenario assumptions; replace them with a measured baseline.
2,232
Task hours per week
€2,901,600
Annual cost allocated to this work
892.8
Potentially released hours per week
€1,160,640
Annual gross value of that capacity
Hours = people × weekly hours × task share. Allocated cost = people × annual loaded cost × task share. Potential capacity multiplies each by the releasable share.
This is not net ROI or a payroll saving. Necessary manual work remains. Adoption and quality must be measured; actual uptake may be lower. Implementation investment, model and hosting costs, maintenance and supervision are excluded. Cash savings require a separate spending decision; otherwise the benefit is capacity available for other work.