Implementation plan
What we fix first, how long it takes and what stops leaking. 8 initiatives across 3 departments. €480-645K illustrative annual gross value.
Priorities at a glance
- 8 initiatives across 3 departments
- €480K to €645K in illustrative annual gross value
- Sample target: hold sync and EDI order repair in production in month 1
- Target: every retailer penalty checked against evidence, every held lot blocked in Sage X3
Automation Opportunity Map
The goal is not to add AI on top of chaos. The goal is to turn repeated fires into infrastructure: context assembled automatically, decisions routed to the right level, exceptions escalated only when human judgment is actually needed. The figures below show direct value by initiative. Broader operational value is modeled separately.
Matching and updates use deterministic rules. An agent can classify a free-text request, gather records or draft a response. Software-enforced access, validation, duplicate handling and named human approvals govern consequential actions.
The two estimates (direct value by initiative; projected annual value by operational effect) are alternative, overlapping views. Do not add them. Ranges are teaching assumptions without source measurements: volumes, time, loaded cost and error cost require validation. Investment, operation and adoption ramp remain to be deducted.
Implementation Timeline
Weeks are relative to implementation start; months represent four four-week blocks. Dependent work can be prepared in parallel with test fixtures, but production release waits for sync acceptance. This is a scenario schedule.
EDI Order Repair
Weeks 2 to 4
Hold Sync
Weeks 2 to 5
Penalty Recovery
Weeks 3 to 8
Complaint Files
Weeks 4 to 7
Promo-to-Plan
Weeks 5 to 11
Shelf-Life Picking Rules
Weeks 6 to 9
Label Change Workflow
Weeks 7 to 11
Recall Readiness
Weeks 9 to 14
Plant 2 rollout and full portal coverage
Weeks 13 to 16
Month 1: EDI order repair and hold sync go live. Penalty recovery starts on the largest retailer. Every proposed fix and every status change is checked by a person during this phase.
Month 2: Penalty packs cover all four portals. Complaint files and promotion calendar in progress. First disputes filed from prepared packs, each approved by Karine.
Month 3: Promo-to-Plan used for the spring promotions. Shelf-life rules active at the dock. Label workflow live. Target: measure hours and refusals against the January baseline.
Month 4: Recall readiness tested with a new mock recall. Plant 2 rollout complete. A second planner and a second quality technician run each workflow before handover is accepted.
Projected Annual Value
Direct initiative value counts each build on its own. Projected value adds shared effects, such as fewer refusals once holds, picking rules and promotion data line up. Released capacity means hours moved from re-keying and chasing to planning, quality and customer work; no headcount reduction is assumed. Write-off and penalty effects are estimated on 2025 data and must be measured after go-live.
How much time could this free up?
Choose one non-overlapping task category and the people who actually perform it. These inputs are scenario assumptions; replace them with a measured baseline.
2,232
Task hours per week
€2,901,600
Annual cost allocated to this work
892.8
Potentially released hours per week
€1,160,640
Annual gross value of that capacity
Hours = people × weekly hours × task share. Allocated cost = people × annual loaded cost × task share. Potential capacity multiplies each by the releasable share.
This is not net ROI or a payroll saving. Necessary manual work remains. Adoption and quality must be measured; actual uptake may be lower. Implementation investment, model and hosting costs, maintenance and supervision are excluded. Cash savings require a separate spending decision; otherwise the benefit is capacity available for other work.