EMS subcontractor · PCB assembly and box build for industrial customers · 1 site, 3 SMT lines · 180 employeesThis War Map shows how we turn an operational review into an implementation plan. The dates show a possible sequence; the scope and schedule of a real engagement are agreed with you.
Findings
Where work gets held up, who has to step in, and what it costs in this example.
Slow quotes lose business
9 days on average to answer an RFQ. Quotes sent within 5 days win more than twice as often as those sent after 10.
Shortages handled line by line
85 open lines checked by hand every week. 23% of jobs start with an incomplete kit, and €640K of kits and WIP waits on missing parts.
Obsolescence found late
31 end-of-life or not-recommended parts sit on active boards with no approved alternate. Customer sign-off on an alternate takes 34 days.
Returns analysed without history
Test results for 2 of 5 benches are not linked to serial numbers. The same failure at two customers went unconnected for five weeks.
Illustrative time allocation for 11 interview roles
- Searching and re-keying component data
- 29%
- Engineering and costing work
- 24%
- Chasing suppliers and customers
- 21%
- Replanning and partial-kit work
- 14%
- Decisions
- 12%
These scenario percentages total 100%. They describe the 11 interview roles only and are not extrapolated to the 180 employees.
64% of the time goes to component data, chasing and replanning. 36% remains for engineering, costing judgement and decisions.
SOP vs. Reality
Every RFQ starts with a BOM in a different format. Mathieu cleans it, matches the parts, then prices each line on distributor sites for three quantities. Labour comes from his memory of similar jobs. The quote leaves after 9 days on average, and the reason for a loss is rarely recorded.
The shortage list is rebuilt every Monday from a Sage X3 export and a tour of distributor sites. Confirmed dates live in Excel, so the ERP plans on old dates. When a part is short, the line often starts anyway, and the missing parts are fitted by hand after reflow.
Notices arrive in a shared mailbox and are sorted by hand. The where-used search only works on manufacturer part numbers, so parts stored under distributor references are missed. The alternate is often ready in days; the customer's engineering approval takes over a month.
The analysis itself is skilled work. The delay comes before it: finding the test log on the right bench, then pulling traceability from the MES. Each return is closed on its own, so patterns across customers stay hidden.