Specialty chemicals formulator · 2 sites near Lyon · 160 employeesThis War Map shows how we turn an operational review into an implementation plan. The dates show a possible sequence; the scope and schedule of a real engagement are agreed with you.
Implementation plan
What to fix first, in what order, and who keeps each decision. 7 initiatives across 4 departments. €520-780K illustrative annual gross value, of which €460-685K is direct initiative value.
Priorities at a glance
- 7 initiatives across 4 departments
- €520K to €780K in illustrative annual gross value
- Sample target: standard document requests answered in 1-2 working days by month 2
- Regulatory sign-off, batch release, ADR signature and price changes stay with named people
Automation Opportunity Map
The goal is not to add AI on top of chaos. The goal is to turn repeated fires into infrastructure: context assembled automatically, decisions routed to the right level, exceptions escalated only when human judgment is actually needed. The figures below show direct value by initiative. Broader operational value is modeled separately.
Matching and updates use deterministic rules. An agent can classify a free-text request, gather records or draft a response. Software-enforced access, validation, duplicate handling and named human approvals govern consequential actions.
The two estimates (direct value by initiative; projected annual value by operational effect) are alternative, overlapping views. Do not add them. Ranges are teaching assumptions without source measurements: volumes, time, loaded cost and error cost require validation. Investment, operation and adoption ramp remain to be deducted.
Implementation Timeline
Weeks are relative to implementation start; months represent four four-week blocks. Dependent work can be prepared in parallel with test fixtures, but production release waits for sync acceptance. This is a scenario schedule.
Document Request Desk
Weeks 2 to 6
Certificate Assembly
Weeks 3 to 7
Cost Watch
Weeks 3 to 8
Supplier SDS Triage
Weeks 4 to 10
Release Queue
Weeks 5 to 9
ADR Paperwork
Weeks 6 to 11
Technical Answers
Weeks 7 to 12
LIMS to Sage X3 Interface
Weeks 12 to 16
Month 1: Document request desk and certificate assembly go live on standard cases. Nadia and Julien review every output. Cost watch starts capturing price notices.
Month 2: Supplier SDS triage works through the backlog of 61, oldest first. Release queue running on both sites. Sample target: standard document requests answered in 1-2 working days.
Month 3: ADR paperwork prepared from master data, with a second adviser in training. Technical answers start with the most requested product families. First monthly indexation run approved by finance.
Month 4: LIMS to Sage X3 interface started. All 7 initiatives in production. Target: measure released capacity and indexation lag against the War Map baseline. Handover is accepted when a second operator can run each flow.
Projected Annual Value
Released capacity means regulatory, lab and logistics specialists spend their hours on classification, testing and safety instead of copying data. No role is removed. Margin recovered on indexed contracts is counted once, in its own line, and depends on contract terms. All figures are illustrative.
How much time could this free up?
Choose one non-overlapping task category and the people who actually perform it. These inputs are scenario assumptions; replace them with a measured baseline.
2,232
Task hours per week
€2,901,600
Annual cost allocated to this work
892.8
Potentially released hours per week
€1,160,640
Annual gross value of that capacity
Hours = people × weekly hours × task share. Allocated cost = people × annual loaded cost × task share. Potential capacity multiplies each by the releasable share.
This is not net ROI or a payroll saving. Necessary manual work remains. Adoption and quality must be measured; actual uptake may be lower. Implementation investment, model and hosting costs, maintenance and supervision are excluded. Cash savings require a separate spending decision; otherwise the benefit is capacity available for other work.
How We Work
War Map
A real engagement is scoped in the Strategy Session and may begin with a War Map or a bounded Feasibility Sprint.