Battery-pack manufacturer scaling from pilot to series · 1 plant in Hauts-de-France · 140 employeesThis War Map shows how we turn an operational review into an implementation plan. The dates show a possible sequence; the scope and schedule of a real engagement are agreed with you.
Implementation plan
What to fix before volume doubles, in what order, and who signs off. 7 initiatives across 4 departments. €453-690K illustrative annual gross value, of which €395-585K is direct initiative value.
Priorities at a glance
- 7 initiatives across 4 departments
- €453K to €690K in illustrative annual gross value
- Sample target: engineering changes effective in 10-12 days by month 3
- Effectivity dates, PPAP signature, UN38.3 decisions and grant reports stay with named people
Automation Opportunity Map
The goal is not to add AI on top of chaos. The goal is to turn repeated fires into infrastructure: context assembled automatically, decisions routed to the right level, exceptions escalated only when human judgment is actually needed. The figures below show direct value by initiative. Broader operational value is modeled separately.
Matching and updates use deterministic rules. An agent can classify a free-text request, gather records or draft a response. Software-enforced access, validation, duplicate handling and named human approvals govern consequential actions.
The two estimates (direct value by initiative; projected annual value by operational effect) are alternative, overlapping views. Do not add them. Ranges are teaching assumptions without source measurements: volumes, time, loaded cost and error cost require validation. Investment, operation and adoption ramp remain to be deducted.
Implementation Timeline
Weeks are relative to implementation start; months represent four four-week blocks. Dependent work can be prepared in parallel with test fixtures, but production release waits for sync acceptance. This is a scenario schedule.
Morning Shortage Brief
Weeks 2 to 6
Dangerous Goods Pack
Weeks 2 to 5
Grant Report Preparation
Weeks 3 to 6
Change Propagation
Weeks 4 to 10
Line-3 Traceability
Weeks 5 to 13
PPAP Assembly
Weeks 6 to 11
Customer Ramp-Up Status
Weeks 7 to 10
Battery Passport Data Model
Weeks 13 to 16
Month 1: Morning shortage brief and dangerous goods pack go live. Sarah and Kevin check every output. Grant evidence collection starts for the current period.
Month 2: Change propagation runs on new changes, with engineering approving each one. Line-3 traceability build starts. PPAP assembly begins with the two packages due first.
Month 3: Customer status reports drafted from live data. Sample target: changes effective in 10-12 days and line-stop hours from shortages down by a third.
Month 4: Line-3 traceability in production and battery passport data model started. All 7 initiatives running. Handover is accepted when a second person can run and recover each flow.
Projected Annual Value
Released capacity goes back to engineering, quality and supplier work while volume doubles. No role is removed; the same team absorbs a larger volume. Margin brought forward is timing within the year and is shown apart from capacity. All figures are illustrative.
How much time could this free up?
Choose one non-overlapping task category and the people who actually perform it. These inputs are scenario assumptions; replace them with a measured baseline.
2,232
Task hours per week
€2,901,600
Annual cost allocated to this work
892.8
Potentially released hours per week
€1,160,640
Annual gross value of that capacity
Hours = people × weekly hours × task share. Allocated cost = people × annual loaded cost × task share. Potential capacity multiplies each by the releasable share.
This is not net ROI or a payroll saving. Necessary manual work remains. Adoption and quality must be measured; actual uptake may be lower. Implementation investment, model and hosting costs, maintenance and supervision are excluded. Cash savings require a separate spending decision; otherwise the benefit is capacity available for other work.